Glenmore PRV & Corridor Improvements

Project type
Water
Project phase
Construction
Project contact
Nick Van Dalen, Engineering Tech. II, 250-766-5650, nvandalen@lakecountry.bc.ca
Active construction project
Yes
Schedule

Wednesday April 16, the contractor will finish shouldering in the Seaton Road paving area. Single lane alternating traffic control will be in place along Seaton Road, between Glenmore Road and Dick Road.

Thursday April 17, the contractor will finish some curbing in the project area. A single lane road closure will be in place on Glenmore Road, between Hwy 97 and Mountview Road, from 9am - 3pm. 

Single Lane Road closure:

Image

Anticipated overall Project completion is ahead of scheduled. Originally estimated for mid-May completion is now planned for April 17, 2025.

Project budget

$750,000

Project status
In Progress
Watermain Installation - Complete
Glenmore Road Paving - Complete
Seaton Road Paving - Complete
Curbing and Shouldering finishing works on Wednesday, April 16 and Thursday April 17
Project description

The Glenmore PRV & Improvements project will install a section of watermain from the Glenmore Booster Station to Seaton Road, and remove two aging pressure reducing valve (PRV) stations. 

The water system works are required in accordance with life cycle asset management. While essential water infrastructure work is underway in the area, there is opportunity to restore pavement from Hwy 97 to Dick Rd. The existing pavement surface is deteriorating and requires resurfacing.  Combining water and road works achieves efficiencies for the District's capital project funding and minimizes any duplication in disruptions.  Improving safety and reducing ongoing operational costs are outcomes of the project.

Project Area  Details:  