Glenmore PRV & Corridor Improvements

Project type
Water
Project phase
Construction
Project contact
Nick Van Dalen, Engineering Tech. II, 250-766-5650, nvandalen@lakecountry.bc.ca
Active construction project
Yes
Schedule

Project underway, anticipated project completion is mid May.

March 25th Update  - Road Closure zone updated - see Alternate Route Map below

Project budget

$750,000

Project status
In Progress
Beginning March 17, sections of Seaton Rd will be closed to all through traffic Monday - Friday between 7:30am and 4:30pm.
Please refer to the Road Closure Work Area and Alternate Route Map below and plan to use alternate routes.
Updates to traffic impacts and road resurfacing scheduling will be posted here.
Project description

The Glenmore PRV & Improvements project will install a section of watermain from the Glenmore Booster Station to Seaton Road, and remove two aging pressure reducing valve (PRV) stations. 

The water system works are required in accordance with life cycle asset management. While essential water infrastructure work is underway in the area, there is opportunity to restore pavement from Hwy 97 to Dick Rd. The existing pavement surface is deteriorating and requires resurfacing.  Combining water and road works achieves efficiencies for the District's capital project funding and minimizes any duplication in disruptions.  Improving safety and reducing ongoing operational costs are outcomes of the project.

Project Area  Details:  

Image

Road Closure Work Area and Alternate Route Map:

Image