Project type
Roads and Mobility
Project phase
Construction
Project contact
A. Chatten, Senior Eng. Tech. , 250-766-5650, achatten@lakecountry.bc.ca
Active construction project
Yes
Schedule
Third week of March until project completion anticipated end of June.
Project budget
$2,800,000
Project status
In Progress
Neighbourhood information meeting March 19th, 6 pm, in the parking area east of
the Woodsdale tennis courts, at the corner of Woodsdale Rd. and Oyama Rd.
Construction activities will commence March 24th. Traffic control and Route 23
transit accommodations will be in place during construction. Please see alternate route map
below.
the Woodsdale tennis courts, at the corner of Woodsdale Rd. and Oyama Rd.
Construction activities will commence March 24th. Traffic control and Route 23
transit accommodations will be in place during construction. Please see alternate route map
below.
Project description
Lodge Rd. improvements, between Sherman Rd. and Woodsdale Rd., will include drainage, road
renewal, curb and gutter, sidewalk installation on one side, transit stop improvements and
intersection improvements. To complement active transportation in the area, and extend seasonal use, the Rail Trail will be paved from Woodsdale Rd. to the Quail Trail access connection south of the Lodge Rd. crossing.
The project is guided by the District's Mobility Improvement Program
(MIP) and design was completed in 2024. The road is in poor condition and requires renewal. This
important section of road serves as a neighbourhood connection to schools and the town centre.